PROJECT #728 - NORTH KANATA TRUNK SEWER
- Cory Houle
- Jun 10, 2021
- 1 min read
Updated: Mar 1, 2022
Project Location : Kanata – Herzberg Rd and Carling Ave
Project team :
PM: Nick Bray
PCs: Maxime Tremblay & Cassidy Mercier
Site Superintendent: Bruno Mongeon
Foreman: Adam Burri & Nathan St-Louis
Project duration:
Start: June 2018
Estimated Finish: July 2021
Project Info:
Sanitary sewer line and watermain installation completed
Greenbelt reinstatement completed
Flume and manhole installation in front of pumping station
Completion of the road reconstruction.