Project location: Fernbank Landing, Stittsville, EQ Homes
Project team:
Operations Manager - Nick Bray
Project Coordinator - Travis Smith
Site Super - Renzo Burri
Foreman - Adam Burri
Project duration:
Project Start: November 19, 2019
Project Completion July 2021
Site Info:
Main work being completed: Site prep and earthwork, Watermain, Storm and Sanitary Sewer installation, Building Excavation and Backfill, Utilities, Landscaping, and Curb & Sidewalk
Install services for 58 units of townhouses