Project location: Ottawa, ON
Project team:
Operations Manager - Nick Bray
Project Manager: Dominick Violante
PC/QC - Siavesh Bahmani
Site Super - Scott Leduc
Foreman - Jonathan Flynt
Project duration:
Project Start: October 2021
Project Completion: June 2022
Site Info:
Sanitary, Storm, & Water Main installation including all appurtenances
New electrical & lighting installations
Installation of Ret. Wall along Rideau Canal
Storm Sewer replacement along Col. By Drive
New Sidewalks, islands, medians, and asphalt on Main Street, Lees Avenue, Echo Drive, Col. By Drive
Landscaping