Project Location: Rockland, ON
Project Team:
Operations Manager - Chace Albright
Project Manager - Alex Secord
QC/PC - Mahmoud Awada
Site Super - Renzo Burri
Project Duration:
Start: September 2019
Completion: March 2022
Project Info:
Upgrading the existing sewage treatment plant with a new headworks building that has an underground tank and can hold up to 4000 m3 of live sewer
Upgrading the existing pump station and installing new pumps that can take on heavier sewage flow rates.
This comes as the City of Clarence-Rockland is one of the fast growing municipalities in eastern Ontario.