PROJECT #766 - MISEMA RIVER BRIDGE


Project location: Kirkland Lake, ON - Misema River


Project team:

  • Operations Manager - Chace Albright

  • Project Manager - Dominick Violante

  • Site Super - Nathan St Louis

Project duration:

Project Start: June 2021

Project Completion: November 2021


Site Info:

  • Subcontract to J& P Leveque

  • Partial Depth Concrete repairs to Deck, Abutments, Piers, & Barrier walls

  • Waterproof Deck

  • Concrete Sealer

  • Thermally Sprayed Anode