Project location: Carleton Place, ON
Project team:
Operations Manager - Chace Albright
Project Manager - Dominick Violante
Site Super - Josh Sturgess
Project duration:
Project Start: June 2021
Project Completion: November 2021
Site Info:
Bell Street - Rehab all underground utilities - new curbs and asphalt
McArthur Island Watermain & Gillies Bridge rehabilitation - Pier & wing wall rehab and repave
Bridge Street - Complete street rehab including new sidewalks, curbs, electrical, lighting, paving
Central Bridge replacement - Complete demolition and new bridge build, including architectural design elements (form lining), new retaining walls, lookout platforms